The Stavria project is currently Voltalia’s biggest construction site in Greece. It consists of five PV projects with a total capacity of 12MW, forming a cluster in the Peloponnese 10km East of Tripoli in the Agiorgitika area at an altitude of 700m.
The plot status is private, covering a total surface of 18 ha, with no inhabitants and no agriculture activities.
Construction began in December 2020 and the projects will be operational by October 2021.
Once completed, this first medium-scale project will quadruple Voltalia’s assets in Greece and set a path for the next projects currently under development in the country.